Professional Installation Services by MacroAir Field Services

Contact Us for Custom Quote 

Installation services are available for MacroAir fans.

The above pricing is per unit. Quantity of installation services must match the total number of fans you wish to have installed.* Not applicable for the Macroair Airlite fan.

  • MacroAir's Responsibilities

    MacroAir Responsibilities:

    - Test and verify customer’s electrical power source.

    - Furnish a scissor-style lift that will reach up to 32 ft.

    - Verify mounting technique (I-beam, bar joist, glulam beam, etc.).

    - Attach fan mount to mounting structure.

    - Attach extension tube to upper mount.

    - Attach extension tube to fan power unit (if it’s a multi-fan network, ensure hanging fans in address order).

    - Secure the safety cable to the mounting structure.

    - Attach safety cable to the power unit.Install disconnect switches if provided.

    - Provide power from the electrical panel to fan disconnect up to 150ft (Additional distance will be an additional cost).

    - Route power wiring from power unit to customer-provided disconnect switch.

    - Provide breaker for electrical panel.

    - Terminate all electrical connections.

    - Mount fan controller at ground level (1/2 EMT conduit will be run to the ceiling deck height).

    - Route Cat5e shielded cable from fan to controller up to 100ft to power unit. (Additional distance will be an additional cost)

    - Terminate all control connections.

    - Install guy wires.Install fan blades and safety retainer links.

    - Customer training of fan operations if electric is in place.Installation to be performed during regular working from 7:00 AM to 5:00 PM M-F.

  •  Customer Responsibilities:

     Customer Responsibilities:

    - Verify availability of 208–204 single-phase power in the building.

    - Verify available breaker space in available 208-240 single-phase panel.

    - Any conduit/electrical cable run in excess of what is described in the above scope of work will be an additional charge.

    - Specialty lifts will require additional costs – including but not limited to: snorkel lifts, narrow aisle lifts, lifts reaching beyond 32ft, and scaffolding.

    - Any required electrical permits are the responsibility of the customer.

    - Run Firewire or tie into fire suppression system

    - Span the difference between beams to give mountable surface. MacroAir can do this for an additional fee contact for a custom quote.