MacroAir Responsibilities:
- Test and verify customers electrical power source.
- Furnish a scissor style lift that will reach up to 32ft
- Verify mounting technique (I-beam, bar joist, glulam beam, etc.).
- Attach fan mount to mounting structure.
- Attach extension tube to upper mount.
- Attach extension tube to fan power unit (if it’s a multi-fan network, ensure hanging fans in address order).
- Secure the safety cable to mounting structure.
- Attach safety cable to power unit.
- Install disconnect switches if provided.
- Provide power from the electrical panel to fan disconnect up to 150ft (Additional distance will be an additional cost).
- Route power wiring from power unit to customer provided disconnect switch.
- Provide breaker for electrical panel.
- Terminate all electrical connections.
- Mount fan controller at ground level (1/2 EMT conduit will be ran to the ceiling deck height).
- Route Cat5e shielded cable from fan to controller up to 100ft to power unit. (Additional distance will be an additional cost)
- Terminate all control connections.
- Install guy wires.
- Install fan blades and safety retainer links.
- Customer training of fan operations if electric is in place.
- Installation to be preformed during regular working from 7:00AM to 5:00PM M-F.
Customer Responsibilities:
- Verify availability of 208 – 204 single phase power in the building.
- Verify available breaker space in available 208-240 single phase panel.
- Any conduit/electrical cable run in excess of what is described in the above scope of work will be an additional charge
- Specialty lifts will require additional costs – including but not limited to: snorkel lifts, narrow aisle lifts, Lifts reaching beyond 32ft, scaffolding.
- If electrical permits are required, those will be the responsibility of the customer.
REVIEWS (0): Installation Services